Finland probes Google-owned firm over 300+ hectares of forest cleared for data center

Editorial illustration: A large magnifying glass rests over tree stumps in a miniature forest landscape beside a translucent industrial building, with evergreen trees and lakes in the background.

In brief

  • Finnish authorities are investigating Google-owned Tuike Finland Oy over forest clearing in Muhos.
  • More than 300 hectares were felled; Finnish law requires an impact assessment above 200 hectares.
  • Felling reportedly continued after a May 2026 determination that an assessment was required.
  • Google says it complied with Finland's Forest Act.
  • Google announced a €13 billion Finnish data center investment on September 9, 2026.

What the complaint says

The probe traces back to the Finnish Association for Nature Conservation, which alerted authorities and filed a complaint in September 2026. Investigators are looking at whether the company breached environmental regulations during clearing work for new data center developments in Muhos and Kajaani.

It comes down to timing.

Finnish law requires an environmental impact assessment (known locally as YVA, and internationally as an EIA) before permanent clear-cutting of more than 200 hectares. Clearing at the Muhos site, in Leppiniemi, began in March 2026. In late April the company asked for an exemption from the assessment requirement, and by May the project had moved into a formal EIA process. Tree felling reportedly kept going into the summer, after the May determination that an assessment was required, according to Crypto Briefing.

Did the felling need to wait for that assessment? That's the question investigators are working through.

Google's position

Google hasn't conceded the point. Its defense rests on forestry law, according to the report:

Google maintains that it complied with Finland’s Forest Act.

The conservation group's complaint isn't built on that statute, though. It centers on the 200-hectare assessment threshold, which the Muhos clearing exceeded by more than 100 hectares.

What's at stake for the €13 billion buildout

On September 9, 2026, Google announced a €13 billion investment in data centers and infrastructure across four locations in Finland. The Muhos land is part of a bigger footprint: in 2024, Google bought 1,400 hectares in Muhos and Kajaani from Metsähallitus (the state forestry agency) for €27 million.

The outcome isn't settled. If authorities conclude the clearing should have waited, Crypto Briefing's analysis says the consequences could range from delays to financial penalties.

Frequently asked questions

What does Finnish law require before large-scale forest clearing?

Finnish law requires an environmental impact assessment, known locally as YVA and internationally as an EIA, before permanent clear-cutting of more than 200 hectares. The Muhos site saw more than 300 hectares felled.

Why is Google's Finnish subsidiary under investigation?

Authorities are examining whether Tuike Finland Oy breached environmental regulations during clearing for data centers in Muhos and Kajaani. The probe followed a September 2026 complaint from the Finnish Association for Nature Conservation, and clearing reportedly continued after a May determination that an assessment was required.

What could happen if Finnish authorities rule against Google?

According to Crypto Briefing's analysis, if authorities conclude the clearing should have waited, the consequences could range from delays to financial penalties. Google maintains it complied with Finland's Forest Act.