xAI's Memphis gas turbines spotlight shift to off-grid power for AI data centers

Editorial illustration: Two gas turbines with tall exhaust stacks sit beside a cutaway data center filled with blue-lit server racks. Pipes connect the structures, with electricity pylons in the distance.

In brief

  • Grid approval for new data centers can take up to a decade, Crypto Briefing reported.
  • xAI's Memphis Colossus site had 35 turbines, roughly 422 MW of nameplate capacity, at peak.
  • Mississippi regulators upheld the Southaven air permit on November 11, 2026, despite community appeals, Crypto Briefing reported.
  • NAACP lawsuit alleging Clean Air Act violations survived motions to dismiss in October 2026, Crypto Briefing reported.

Why build your own power plant?

Plugging a new data center into the electric grid can mean waiting as long as a decade for approval, according to Crypto Briefing's analysis.

A growing number of developers aren't waiting.

They're building their own natural gas plants on site instead. The Colossus campuses exist to train AI models such as Grok, and xAI decided local utilities couldn't supply enough steady power on its timeline, Crypto Briefing reported.

Permits in Memphis and Southaven

Some of the Memphis turbines reportedly operated without permits. In July 2025, Colossus 1 received a permit for 15 permanent turbines with a combined capacity of approximately 247 megawatts, according to the report (which doesn't cite the permit documents themselves).

Colossus 2 sits in Southaven, Mississippi. Regulators approved 41 gas turbines there in March 2026 (around 1.2 gigawatts of capacity), and on November 11, 2026, the Mississippi Department of Environmental Quality Permit Board upheld that air permit despite community appeals, Crypto Briefing reported. Before the move to permanent equipment, unpermitted turbines in Southaven reportedly peaked at 69 units; the remaining ones are scheduled to be phased out by July 2027.

The sites aren't relying on turbines alone, though. They're also adding grid capacity in increments of 150 to 300 MW and using battery storage, according to the outlet.

The NAACP lawsuit

Community concerns center on what gas turbines release into the local air. In April 2026, the NAACP filed a federal lawsuit against xAI alleging Clean Air Act violations tied to emissions from both temporary and permanent turbines. Judges denied motions to dismiss in late October 2026, Crypto Briefing reported, so the case continues and it's still unresolved.

Frequently asked questions

What is behind-the-meter power for data centers?

It's the industry term for electricity generated on site rather than drawn from the grid. Crypto Briefing reported that a growing number of developers are building their own natural gas plants because a new grid connection can take as long as a decade to approve.

Why did xAI install gas turbines at its Colossus sites?

The Colossus campuses train AI models such as Grok. According to Crypto Briefing, xAI decided local utilities couldn't supply enough steady power on its timeline, so it had its first turbines running at the Memphis site by mid-2024.

What is the NAACP lawsuit against xAI about?

In April 2026, the NAACP filed a federal lawsuit alleging Clean Air Act violations tied to emissions from xAI's temporary and permanent turbines. Crypto Briefing reported that judges denied motions to dismiss in late October 2026, so the case hasn't been resolved.